How to schedule production in a print shop

To schedule production in a print shop, start from each order's in-hands date and work backward to the day it must ship, the day it must come off the press, and the day its blanks and approved art must be in the building. Then size every job in hours on the press that will run it (setup time plus pieces divided by realistic speed), fill each press day up to its real capacity, and refuse to book any job that is still waiting on art approval, payment or goods. That's the whole method; the rest is discipline.
Below is the method in detail, with a worked example you can copy into a spreadsheet or a whiteboard.
Why "first in, first out" breaks down
Many shops start by printing jobs in the order they came in. It works when the shop is quiet. It fails as soon as three things happen at once: a rush order lands, a big job's blanks arrive late, and a customer sits on their proof for a week. Suddenly the job at the top of the pile can't run, the one behind it is due tomorrow, and nobody knows whether Thursday is already full.
A real production schedule answers three questions at a glance:
- What has to be done by when? (due dates converted to press dates)
- How much can each press actually do per day? (capacity)
- Which jobs are truly ready to run? (gates)
Step 1: Turn in-hands dates into press dates
The customer gives you an in-hands date: the day the shirts must be in their hands. Your schedule needs a press date. Work backward:
- In-hands date: when the customer needs it.
- Minus transit: if it ships, the carrier's ground time to that address. If it's a pickup, zero.
- Minus finishing and packing: folding, bagging, counting, boxing. Many shops allow a day for this on larger orders.
- Minus curing or drying buffer, where your process needs it.
- = Latest press date.
Then go back further for what the press date depends on:
- Blanks in by: the press date minus one working day, so someone can count them before the job is set up. (See checking in blank garments.)
- Art approved by: early enough to order blanks and burn screens or digitize.
Write the latest press date on the order. That date, not the in-hands date, is what the schedule sorts by.
Step 2: Size every job in hours
A job is one decoration on one order: the front print on 144 tees is a job, the left chest on the same tees is another. Each job's time on a press is roughly:
Job time = setup time + (pieces ÷ realistic pieces per hour)
"Realistic" matters. Use what your crew actually averages including loading, reloading and small stops, not the number on the press brochure. If you don't know it, time a few ordinary jobs and use the average.
Worked example
Say your shop has two machines and these numbers (an example, not a benchmark):
| Machine | Runs | Realistic speed | Setup per job | Hours a day |
|---|---|---|---|---|
| 6-color auto | Screen print | 300 pieces/hour | 45 min | 8 |
| Manual 4-color | Screen print | 60 pieces/hour | 30 min | 8 |
And this week's jobs:
| Job | Pieces | On the auto | On the manual |
|---|---|---|---|
| A: 2-color front, 600 tees | 600 | 45 min + 2 h = 2 h 45 min | 30 min + 10 h = 10 h 30 min |
| B: 1-color back, 600 tees | 600 | 45 min + 2 h = 2 h 45 min | not sensible |
| C: 3-color front, 48 hoodies | 48 | 45 min + 10 min = 55 min | 30 min + 48 min = 1 h 18 min |
| D: 1-color left chest, 24 tees | 24 | 45 min + 5 min = 50 min | 30 min + 24 min = 54 min |
Two things jump out. First, the big runs belong on the auto, obviously. Second, small jobs are nearly all setup on either machine, which is why many shops batch small runs by ink color or send them to the manual so the auto stays on long runs. (More on that in batching jobs by decoration method.)
Step 3: Fill each press day to real capacity
Now place jobs on days, earliest press date first. A press with 8 hours a day doesn't get 8 hours of jobs: leave room for cleanup, screen changes that run long and the rush order that will show up on Wednesday. A common habit is to plan a press to something like 80 to 85 percent of its hours and treat the rest as buffer; pick a figure that matches your own shop's history.
Using the example above, Monday on the auto could hold job A (2 h 45 min) and job B (2 h 45 min) with room left over for job C. If job C's press date is Thursday, you can still run it Monday if it's ready, but don't let early work push a due job off the schedule.
When a day goes over capacity, you have four honest options: move a job to another machine that runs the method, move it to an earlier day if it's ready, add a shift or overtime, or call the customer about the date now, not on the due day. Our post on press capacity planning goes deeper on working out what each machine can carry.
Step 4: Gate every job on art, payment and goods
The biggest scheduling mistake is booking jobs that can't run. A job is only ready when all three of these are true:
- Art is approved: the customer has signed off on a specific proof version. (See a reliable art approval process.)
- Payment is in: whatever you require before production, whether that's nothing, a deposit or payment in full.
- Goods are here: every size and color is counted and on the shelf.
Keep jobs that fail any check in a separate "waiting" column. They have a press date, so you know they're coming, but they don't take a slot until they're ready. When a box arrives or a proof gets approved, the job moves into the queue.
You will sometimes start a job anyway, for a trusted customer or a true rush. Fine, but make it a decision someone takes on purpose and records, not something that happens because the blanks showed up.
Step 5: Put rush jobs in deliberately
Rush jobs aren't a separate system. They get the same treatment, with an earlier press date. When you sort the queue, put rush first, then everything else by earliest press date, on whichever capable press can fit it soonest. Charge for the disruption: our guides on rush order fees and fitting rush orders into a full schedule cover both sides.
A daily routine that keeps the schedule honest
| When | What to do |
|---|---|
| Start of day | Check yesterday's jobs are marked done; move anything unfinished to today or tomorrow |
| Morning | Review the waiting column: which proofs, deposits or boxes came in? Queue those jobs |
| Midday | Look two to three days ahead for overloaded days; fix them now |
| End of day | Confirm tomorrow's first jobs have screens, ink and blanks staged |
Ten minutes a day on this saves the Friday afternoon scramble.
How this works in SKUFlow
In SKUFlow, each decoration on an order becomes a job on the production board, in columns for waiting on the order, queued and in progress. You add each press or machine with the methods it runs, units an hour, setup minutes, hours a day and working days, and a job's estimate is its setup plus its pieces at that speed. The schedule view shows each press's planned hours against its capacity per day, with overbooked days in red, and Plan proposes a schedule with rush orders first, then the earliest in-hands date, on the press that runs the method and can fit it soonest. Orders wait on three checks (art approved, payment, goods here) and their jobs only move to queued once all three are done; you can waive a check or start production anyway. See the help article on planning jobs on your presses.
Common questions
Should I schedule by in-hands date or by the date the order came in?
By the latest date it can come off the press, which you work out from the in-hands date. Order date tells you nothing about urgency. A job that came in last week for an event next month can wait behind a job that came in yesterday for Friday.
How far ahead should I schedule?
Most shops plan the current week in detail and keep a rough view of the next one or two. Further out than that, dates and art change too often to be worth placing on exact days, but you should still see the total hours coming so you can spot a crunch.
What do I do when a job is ready but its press date is far away?
If there's open capacity today and running it early won't bump a job that's due sooner, run it. Early is fine; late isn't. Just don't let "it's ready" push due work off the schedule.
How do I handle outsourced decoration in the schedule?
Keep it off your press rows but on your calendar. Give the decorator a due-back date that leaves you time to pack and ship, and treat the returned goods like a job that needs checking in before it can ship.